A control layer for the Remedy dispatch desk and the shift manager. It ranks every fault by what the site puts at risk, recommends the action, drafts the message for the field team and keeps the history of every visit.
The Alexandria field team receives faults through a manual hand-off and splits them within the shift. Four gaps follow from that.
A fault on a site that feeds many others can wait behind a minor one.
What was done on earlier visits is asked for by phone and chat, not read from the site.
Time on site and work done are not recorded in a form that adds up by site or area.
Access routes and site quirks leave with the engineer who knew them.
Faults sit with the field team that owns them, each carrying its importance score, fault type and the number of sites that depend on it. Unassigned faults can be distributed in one step, most important first.
Each fault is classified and given an assessment: its impact, the upstream sites to check first, whether the site keeps coming back, and which other open faults share the hub. A checklist for the team follows from the fault type.
The dispatcher gets a ready message with the site, address, map link, checks and last visit. It can be edited, copied, or opened in WhatsApp or email. Nothing is sent automatically, and the platform records when the message was marked as sent.
The analytics view ranks areas by the attention they need, shows each team's workload and results, and lists the sites that needed two or more visits in 30 days so their root cause can be reviewed.
Scores run from 0 to 100 and combine facts from the site inventory with live fault and visit data. The weights are starting values, open to tuning with Vodafone and Ericsson engineers.
| Factor | Effect on score |
|---|---|
| Downstream sites in the transmission chain | up to +40 |
| Hub site | +20 |
| Hosts another operator | +12 |
| Site type: dual or second layer, macro, repeater, micro | +12, +10, +5, +3 |
| Non-commercial power supply | +8 |
| LTE 2600 present | +5 |
| Visits in the last 30 days | +8 each, up to +24 |
| Open fault, or open service-affecting fault | +10, +25 |
| Age of the open fault | +2 per day, up to +12 |
Tiers: critical at 60 and above, high at 40, medium at 20, normal below. Dismantled sites score zero.
The platform starts read-only. It reads faults and site data, gives the dispatch desk and the shift manager one view, and writes nothing back until IT and security approve it.
The dashed line is a later step that needs a read-only account and the interface Ericsson approves. The site data comes from the Alexandria inventory workbook and the KMZ file.
Success is judged against a baseline taken before the pilot: time from fault to assignment, time to arrival, time on site, repeat visits and the share of visits with a complete record. Targets are agreed once the baseline exists.